
Solutions · family
AI & DC Power
Battery storage, UPS and switchgear enclosures: floors that carry 50 tonnes, envelopes that do not burn.
- 2,000-3,000 kg/m²
- explosion relief per EN 14994 / NFPA 68
- A1 mineral wool
- liquid-tight steel tray
The power side of the same engineering. A 6 MWh battery rack assembly in a 20 ft footprint weighs 40 to 50 tonnes; a standard container floor carries a fraction of that. Tanax builds the enclosure that does: heavier cross-members, a welded 6 mm steel deck that doubles as a containment tray, explosion relief panels, non-combustible insulation, and cable and cooling provisions positioned to your layout.
Specification
Floor
- Distributed load
- 2,000 kg/m² standard, 3,000 kg/m² option
- Point load
- 5,000 kg per pair of rack feet
- Cross-members
- C 180 × 70 × 5 at ≤ 300 mm
- Deck
- 6 mm S355, welded tight, liquid-tight tray for coolant or suppression water
- 20 ft internal floor area
- ~13.9 m², so ~27.8 t at 2,000 kg/m²
Envelope
- Insulation
- 100 mm mineral wool, Euroclass A1, λ ≈ 0.035 W/m·K. PIR explicitly not recommended
- Lining
- 0.8 mm galvanised sheet on a supporting grid
Safety
- Explosion relief
- panels per EN 14994 / NFPA 68, included as standard, removable on request
- Doors
- insulated personnel door with anti-panic hardware
- Earthing
- dedicated earth points, frame bonded
Coating
- System
- Zn-epoxy 80 + epoxy MIO 120 + PU 60 = 260 µm, ISO 12944 C4-H / C5-M
Provisions
- HVAC openings
- 2 on 20 ft, 4 on 40 and 45 ft, framed and hooded
- Cable transits
- HV / LV transit plate with sealed glands
Shell
- Sizes
- 20 / 40 / 45 ft high cube, 1CCC / 1AAA, CSC with new plate
Cost structure
- Material share of price
- ~39 %, which is why steel indexation is recommended on long programmes
Specification
Floor
- Distributed load
- 2,000 kg/m² standard, 3,000 kg/m² option
- Point load
- 5,000 kg per pair of rack feet
- Cross-members
- C 180 × 70 × 5 at ≤ 300 mm
- Deck
- 6 mm S355, welded tight, liquid-tight tray for coolant or suppression water
- 20 ft internal floor area
- ~13.9 m², so ~27.8 t at 2,000 kg/m²
Envelope
- Insulation
- 100 mm mineral wool, Euroclass A1, λ ≈ 0.035 W/m·K. PIR explicitly not recommended
- Lining
- 0.8 mm galvanised sheet on a supporting grid
Safety
- Explosion relief
- panels per EN 14994 / NFPA 68, included as standard, removable on request
- Doors
- insulated personnel door with anti-panic hardware
- Earthing
- dedicated earth points, frame bonded
Coating
- System
- Zn-epoxy 80 + epoxy MIO 120 + PU 60 = 260 µm, ISO 12944 C4-H / C5-M
Provisions
- HVAC openings
- 2 on 20 ft, 4 on 40 and 45 ft, framed and hooded
- Cable transits
- HV / LV transit plate with sealed glands
Shell
- Sizes
- 20 / 40 / 45 ft high cube, 1CCC / 1AAA, CSC with new plate
Cost structure
- Material share of price
- ~39 %, which is why steel indexation is recommended on long programmes
How it is built
The decisions behind the numbers
Start from the rack weight, not the container.
A 20 ft internal floor is about 13.9 m². At 2,000 kg/m² that is 27.8 tonnes. A 6 MWh rack assembly in the same footprint is commonly 40 to 50 tonnes. So 2,000 kg/m² is the floor of the range, not the answer. Send the rack mass, footprint and foot layout and the structural calculation returns the real number, including transport loads and, where the site requires it, seismic cases.
The deck is a containment tray.
6 mm plate welded tight with no plywood. A coolant leak or a suppression discharge is retained inside the module instead of running out through the floor seams.
No PIR in a battery enclosure.
PIR is combustible. Mineral wool at Euroclass A1 is the default and we will argue for it. Where a thermal target of λ ≤ 0.026 W/m·K genuinely binds, PIR is quotable, on request, with the fire consequence stated in writing.
Explosion relief is priced in, not bolted on.
Panels sized per EN 14994 / NFPA 68 are in the base price. If your fire concept does not require them, removing them takes money out.
Priced bottom-up, and it is defensible.
Material at purchase cost, plus co-operation, plus direct hours at a fully absorbed overhead rate. Not a catalogue estimate. As a benchmark: one Nordic armed forces framework pays a ceiling of €80,000 per insulated 20 ft container with no equipment at all. A Tanax technology container with substantially more content sits at well under half of that.
Configurations
Variants and where to find them in the catalogue
- No photograph yet
- No photograph yet
- No photograph yet
45 ft BESS enclosure
- 13,716 mm
- pallet-wide option
- usually stationary, structure can be lightened
- No photograph yet
Non-passthrough variant
- full-length doors, no service aisle
- racks fill the volume
- ~6 % less on 20 ft
- No photograph yet
UPS and switchgear enclosure
- ESD floor
- environmental control
- no explosion relief
Options and what they do to the price
| Change | Effect on a 20 ft |
|---|---|
| Non-passthrough (no personnel door, no service aisle) | −€1,450 |
| Without explosion relief panels | −€990 |
| Standard 8'6" height instead of high cube | −€165 |
| Floor 3,000 kg/m² instead of 2,000 | +€1,800 |
| PIR instead of mineral wool (λ ≤ 0.026 W/m·K) | on request |
Build detail
What the detail photography shows
Standards
What we build to and what we issue
- EN 14994 / NFPA 68
- EN 13501-1
- ISO 12944
- EN 1090-1 EXC2 / EN ISO 3834-2
- ISO 668:2020 Amd 1 / ISO 1161
- CSC 1972
| Standard | What it covers |
|---|---|
| EN 14994 / NFPA 68 | Explosion venting design |
| EN 13501-1 | Reaction to fire, Euroclass A1 |
| ISO 12944 | Coating durability |
| EN 1090-1 EXC2 / EN ISO 3834-2 | Steel execution and welding |
| ISO 668:2020 Amd 1 / ISO 1161 | Dimensions and corner castings |
| CSC 1972 | Safety approval and re-plating |
Documentation issued
Floor structural calculation, explosion relief sizing note, coating specification and thickness report, insulation fire declaration, penetration as-built, CSC plate.
Proof
Deployments with a number in them
- 01
A 200-unit-per-year enclosure programme
Designed and priced bottom-up for a global electronics manufacturer, with a capacity ramp from 4-6 units a month to 17.
Read the case study - 02
600 cells in a 20 ft footprint
Li-ion battery storage and charging enclosure work assessed for two separate Northern European defence and industrial programmes, including a requirement for 300 stored and 300 charging simultaneously, with charging plant, BMS monitoring, capacity testers, cable ladders and fire suppression at ≤ 3 m overall height with an integrated hook-lift frame.
- 03
44 % of available capacity
What a 200-unit 20 ft programme consumes. Stated openly because a supplier who will not tell you that is guessing.
Scope
What the price includes, and what it does not
Included
- Enclosure
- Structural floor with calculation
- Insulation and lining
- Coating system
- Explosion relief
- Framed openings
- Cable transit plates
- Earthing
- Doors and hardware
- Inspection protocol
- CSC plate
Not included
- Battery modules, racking and BMS
- PCS, inverters, switchgear and internal electrical installation
- Cooling and ventilation units
- Fire suppression system and its certification
- Delivery
- Third-party structural review beyond our own calculation
If we have not built exactly this before, we will say so and tell you what we have built that is closest. Two prototype programmes in this factory were delivered below cost because nobody said that early enough. We do not do that any more, to you or to us.
Lead times
By variant
| Variant | Lead time |
|---|---|
| First article | 10-12 weeks |
| Months 1-3 | 4-6 units per month |
| Months 4-8 | 8-12 units per month |
| From month 9 | 17 units per month |
Same ramp as Data Centers.
Engagement
Four ways to buy
Buy a catalogue unit
Pick from 94 published SKUs with full specifications, get a price, get a delivery date.
Modify a catalogue unit
Start from a standard shell and change what needs changing. Fastest route to a non-standard requirement.
Build to your specification
You bring the specification or the drawings, we review them, we build. Prototype and serial priced separately.
Subcontract fabrication
You are the prime, we are the hall. EN 1090-1 EXC2 capacity with AQAP 2110 assurance behind it.
Process
Specification to delivery in five steps
- 01
Send the specification.
A drawing, a tender annex, or three sentences. Whichever you have.
- 02
Review, in writing.
We tell you what is missing or contradictory before anyone quotes. 3-5 working days.
- 03
Quotation.
Bottom-up: material at purchase cost, co-operation, direct hours at a fully absorbed rate. 2-3 weeks for a complex build.
- 04
Design freeze and build.
Changes after freeze are variations, priced and agreed.
- 05
Test, document, deliver.
Factory acceptance where specified, full document pack, delivery and installation where quoted.
FAQ
Questions procurement asks
How much can the floor carry?
2,000 kg/m² as standard, 3,000 kg/m² as an option, with 5,000 kg point loads at rack feet. Give us the rack mass and foot layout and we calculate the real requirement.
Why do you refuse PIR here?
Because it burns. In a battery enclosure the reaction-to-fire class is the safety case.
Is explosion relief included?
Yes, in the base price, sized per EN 14994 / NFPA 68. Taking it out reduces the price.
Do you supply the batteries or the PCS?
No. We build the enclosure and the provisions. That keeps the responsibility boundary clean.
45 ft: is it a good idea?
Only if it is stationary. 13,716 mm is not a standard ISO 668 length, most EU states require a road permit, and sea transport of a 45 ft battery container is rare. If it never moves again, we can lighten the structure and reduce the price.
Can you fix a price for a year?
Yes, with an indexation clause tied to steel. Material is about 39 % of the cost.
Send us the specification. A drawing, a tender annex, or three sentences.
You will get a written review of it inside a week, whether or not you buy anything.
Where to go next
Related families
- Data CentersPre-tested IT modules: the steel, the envelope and the provisions, engineered around your rack layout.
- Generator & DistributionContainerised power generation, distribution and fuel: a camp-scale electrical system in ISO frames.
- CustomOne-offs, prototypes and things that do not have a product code yet.
Related sectors
Related case studies






