Containerized data centerTechnical pages
Cooling of the data center module
Air-cooled at 5 to 10 kW per rack as the typical design point, with the aisle contained and the room kept tight. Higher density and liquid cooling are engineered on request.

N+1 precision cooling
N+1 precision DX units, wall-mounted or in-row, with free cooling and EC fans. One unit can fail or be serviced without the room warming up.
Containment
Hot and cold aisle containment keeps the supply air where the racks take it in. The design point is typically 5 to 10 kW per rack air-cooled.
A tight room
There is no separate fresh-air system, so the room stays tight for the gas suppression. Air exchange runs through the free-cooling dampers.
The technical room
The technical room has its own separate split unit, so the power cabinets and the batteries are conditioned independently of the IT room.
Condensate and refrigerant
Condensate drainage is part of the design, and the refrigerant and condensate lines enter through sealed penetrations.
Higher density
Higher density per rack and liquid cooling are engineered on request. The envelope, the floor and the penetrations are prepared for it; the design point is agreed in the engineering phase.
Specification sheet
| Cooling | |
|---|---|
| Cooling | N+1 precision DX units (wall-mount or in-row) with free cooling and EC fans; hot and cold aisle containment; separate split unit for the technical room; condensate drainage |
| Air | No separate fresh-air system, so the room stays tight for gas suppression; air exchange through free-cooling dampers |
Figures are the published specification of the product family, not of a customer's design. Values marked per project are set in the engineering phase.
The specification sheet is generated from the same data as this page. It is sent with the reply to your enquiry and offered for download when the form is submitted.
Request the specification sheet (PDF)FAQ
Questions procurement asks
What density is the standard design?
Typically 5 to 10 kW per rack air-cooled. Higher density and liquid cooling are engineered on request.
Why no fresh-air system?
A tight room is what the clean-agent suppression needs: the enclosure integrity test per NFPA 2001 / ISO 14520 measures exactly that. Air exchange runs through the free-cooling dampers.
Is the technical room cooled by the same units?
No. It has a separate split unit, so the IT room's cooling is dedicated to the racks.
Send the rack layout. The module is engineered around it.
Rack count, width, depth and the density per rack set the room, the power architecture and the cooling. The specification sheet comes with the reply.
Related
Technical pages of this solution
- Data CentersFactory-built data center modules for edge, enterprise and AI.
- Envelope and securityThe envelope is what the IT never notices: fire from outside held for 60 minutes, a burglar held at RC3, salt air held for decades, and a floor that carries the racks and keeps a leak inside.
- PowerThe technical room holds the power chain: the incoming supply, the architecture from single path to 2N, the conversion to -48 V DC and 230 V AC, the batteries and the distribution to every rack.
- Fire and monitoringClean-agent suppression in a room that is tested to hold it, detection that sees smoke before it is smoke, and a monitoring layer that reports every sensor over SNMP and Modbus.
- Process and factory testThe module is engineered once and built as many times as the programme needs. Before it ships it runs under a load bank in our plant, and the suppression system is tested in the room it protects.