Does a container need a building permit? Germany, Saxony

In Germany, Saxony the governing measure is gross volume. A container whose gross volume stays within 75 m3 falls into the simplified route and is handled as a no filing. Above that line the full building-permit procedure applies. The basis is Sächsische Bauordnung (SächsBO) in der Fassung der Bekanntmachung vom 11. Mai 2016 (SächsGVBl. S. 186), zuletzt geändert durch Artikel 1 des Gesetzes vom 1. März 2024 (SächsGVBl. S. 169), § 61 Abs. 1, in the version of 2016-05-11. The statute is quoted word for word further down this page, in the original language and in translation, so you can check the figure without leaving the site. The authority to contact is Untere Bauaufsichtsbehoerde.

Last verified:

What are the thresholds?

What are the thresholds? Germany
MeasureValueWhen this number appliesProvision
Gross volume, outside the Aussenbereich75 m3Applies to a building outside the Aussenbereich. The provision attaches no condition about habitable rooms, toilets or fireplaces, so an office or sanitary container is verfahrensfrei below this line, as in Bavaria and unlike Brandenburg. The separate 80 m3 figure applies only to charging stations serving public transport.§ 61 Abs. 1 Nr. 1 Buchst. a
Minimum boundary setback3 mThe depth of the setback area is 0.4 H, at least 3 m; in commercial and industrial zones 0.2 H suffices, again at least 3 m. At container wall heights 0.4 H is well under three metres, so the floor governs. The same rule as Brandenburg.§ 6 Abs. 5 Satz 1

The statute, word for word

Original wording

Gebäude mit einem Brutto-Rauminhalt von bis zu 75 m³ und von bis zu 80 m³ für Ladestationen, die der Elektromobilität des öffentlichen Nahverkehrs dienen, außer im Außenbereich

Our translation

buildings with a gross volume of up to 75 m3, and of up to 80 m3 for charging stations serving the electric mobility of local public transport, except in the Aussenbereich

Act
Sächsische Bauordnung (SächsBO) in der Fassung der Bekanntmachung vom 11. Mai 2016 (SächsGVBl. S. 186), zuletzt geändert durch Artikel 1 des Gesetzes vom 1. März 2024 (SächsGVBl. S. 169)
Provision
§ 61 Abs. 1 Nr. 1 Buchst. a
Version of the act
In force from
Text retrieved
Open the official source
Original wording

Die Tiefe der Abstandsflächen beträgt 0,4 H, mindestens 3 m.

Our translation

The depth of the setback areas is 0.4 H, at least 3 m.

Act
Sächsische Bauordnung (SächsBO) in der Fassung der Bekanntmachung vom 11. Mai 2016 (SächsGVBl. S. 186), zuletzt geändert durch Artikel 1 des Gesetzes vom 1. März 2024 (SächsGVBl. S. 169)
Provision
§ 6 Abs. 5 Satz 1
Version of the act
In force from
Text retrieved
Open the official source

Do you need a permit or is a notification enough?

Saxony, like Bavaria and Brandenburg, has no notification step here: a project is either verfahrensfrei or it needs a building permit. A container up to 75 m3 outside the Aussenbereich is verfahrensfrei regardless of whether it has a habitable room.

Original wording

Verfahrensfrei sind

Our translation

The following are procedure-free

Act
Sächsische Bauordnung (SächsBO) in der Fassung der Bekanntmachung vom 11. Mai 2016 (SächsGVBl. S. 186), zuletzt geändert durch Artikel 1 des Gesetzes vom 1. März 2024 (SächsGVBl. S. 169)
Provision
§ 61 Abs. 1
Version of the act
In force from
Text retrieved
Open the official source

Who do you contact?

Untere Bauaufsichtsbehoerde. The lower building supervisory authority of the district or of a town with its own jurisdiction. The governing statute is the Sächsische Bauordnung, not a federal act.

What documents will you need?

  • For a verfahrensfrei project nothing is filed. Responsibility for complying with the substantive rules stays with the developer.
  • Evidence of conformity with the Bebauungsplan where one exists for the plot.
  • A gross-volume calculation demonstrating the 75 m3 line.
  • A site plan with the § 6 setback areas where the works sit near a boundary.

How do the neighbouring jurisdictions compare?

How do the neighbouring jurisdictions compare?
JurisdictionBuilt-up areaGross volumeHeightBoundary setbackDo you need a permit or is a notification enough?Does the exemption cover an office container?
Germany, SaxonyThe statute states no fixed figure75 m3The statute states no fixed figure3 mNo filingYes
Slovakia50 m2The statute states no fixed figure5 m2 mNotificationYes
Czechia40 m2The statute states no fixed figure5 m2 mFull permitYes
PolandThe statute states no fixed figureThe statute states no fixed figureThe statute states no fixed figureNot yet verifiedNotificationYes

All jurisdictions

What to watch out for

  • Three German states, one number, two rules. Bavaria, Saxony and Brandenburg all say 75 m3, but Bavaria and Saxony attach no habitable-room condition while Brandenburg requires a building without habitable rooms, toilets or fireplaces. An office container is therefore verfahrensfrei below 75 m3 in Saxony and Bavaria and is not verfahrensfrei at any volume in Brandenburg. Comparing the numbers alone groups all three together and gets one of them wrong.
  • The 80 m3 figure in the same sub-paragraph does not concern containers. It applies expressly only to charging stations serving the electric mobility of local public transport.
  • The source is the full-text PDF of the current version from the REVOSax portal. The current-version page links to it directly and states the text is valid from 19 March 2024, with no repeal notice of any kind. The PDF breaks a page in the middle of the § 61 sentence, so whole header and footer lines were removed from the extraction by script. The raw text stays on disk beside the cleaned one, so any citation traces back to the PDF.

Please note

This is guidance, not legal advice. The thresholds are quoted verbatim from the statute in force on the date shown, but an individual plot can be subject to a zoning plan, a protection zone or heritage rules that are not reflected here. Confirm your case with the named authority before you order.