Does a container need a building permit? Germany, Bavaria

In Germany, Bavaria the governing measure is gross volume. A container whose gross volume stays within 75 m3 falls into the simplified route and is handled as a no filing. Above that line the full building-permit procedure applies. The basis is Bayerische Bauordnung (BayBO) in der Fassung der Bekanntmachung vom 14. August 2007 (GVBl. S. 588), BayRS 2132-1-B, Art. 57 Abs. 1 Nr. 13 Buchst. a, in the version of 2007-08-14. The statute is quoted word for word further down this page, in the original language and in translation, so you can check the figure without leaving the site. The authority to contact is Untere Bauaufsichtsbehoerde.

Last verified:

What are the thresholds?

What are the thresholds? Germany
MeasureValueWhen this number appliesProvision
Gross volume, outside the Aussenbereich75 m3Applies to a building outside the Aussenbereich, that is inside the built-up area. The measure is VOLUME, not area. A 20 ft container is 38.27 m3 and stays under the line; a 40 ft container is 77.02 m3 and crosses it.Art. 57 Abs. 1 Nr. 1 Buchst. a
Gross volume, in the Aussenbereich20 m3In the Aussenbereich, that is outside the built-up area, the line drops to 20 m3 and applies only to buildings without habitable rooms, toilets or fireplaces that serve neither sales nor exhibition purposes. Only a 10 ft container at 17.78 m3 fits under it.Art. 57 Abs. 1 Nr. 1 Buchst. a
Minimum boundary setback3 mThe depth of the setback area is 0.4 H, or 0.2 H in commercial and industrial zones, but in each case at least 3 m. For a container with a wall height around 2.6 m to 2.9 m, 0.4 H is only about 1.2 m, so the 3 m floor is what governs.Art. 6 Abs. 5 Satz 1

The statute, word for word

Original wording

Gebäude mit einem Brutto-Rauminhalt bis zu 75 m3, außer im Außenbereich, sowie Gebäude ohne Aufenthaltsräume, Toiletten oder Feuerstätten, wenn die Gebäude weder Verkaufs- noch Ausstellungszwecken dienen, im Außenbereich bis 20 m3 Brutto-Rauminhalt

Our translation

buildings with a gross volume of up to 75 m3, except in the Aussenbereich, as well as buildings without habitable rooms, toilets or fireplaces, where the buildings serve neither sales nor exhibition purposes, in the Aussenbereich up to 20 m3 gross volume

Act
Bayerische Bauordnung (BayBO) in der Fassung der Bekanntmachung vom 14. August 2007 (GVBl. S. 588), BayRS 2132-1-B
Provision
Art. 57 Abs. 1 Nr. 1 Buchst. a
Version of the act
In force from
Text retrieved
Open the official source
Original wording

Gebäude mit einem Brutto-Rauminhalt bis zu 75 m3, außer im Außenbereich, sowie Gebäude ohne Aufenthaltsräume, Toiletten oder Feuerstätten, wenn die Gebäude weder Verkaufs- noch Ausstellungszwecken dienen, im Außenbereich bis 20 m3 Brutto-Rauminhalt

Our translation

buildings with a gross volume of up to 75 m3, except in the Aussenbereich, as well as buildings without habitable rooms, toilets or fireplaces, where the buildings serve neither sales nor exhibition purposes, in the Aussenbereich up to 20 m3 gross volume

Act
Bayerische Bauordnung (BayBO) in der Fassung der Bekanntmachung vom 14. August 2007 (GVBl. S. 588), BayRS 2132-1-B
Provision
Art. 57 Abs. 1 Nr. 1 Buchst. a
Version of the act
In force from
Text retrieved
Open the official source
Original wording

Die Tiefe der Abstandsflächen beträgt 0,4 H, in Gewerbe- und Industriegebieten 0,2 H, jeweils aber mindestens 3 m.

Our translation

The depth of the setback areas is 0.4 H, in commercial and industrial areas 0.2 H, but in each case at least 3 m.

Act
Bayerische Bauordnung (BayBO) in der Fassung der Bekanntmachung vom 14. August 2007 (GVBl. S. 588), BayRS 2132-1-B
Provision
Art. 6 Abs. 5 Satz 1
Version of the act
In force from
Text retrieved
Open the official source

Do you need a permit or is a notification enough?

Bavaria has no notification step for these works: a project is either verfahrensfrei, meaning no procedure at all, or it needs a full building permit. A container up to 75 m3 outside the Aussenbereich is verfahrensfrei. A container placed as a site facility is verfahrensfrei with no volume limit whatsoever.

Original wording

Baustelleneinrichtungen einschließlich der Lagerhallen, Schutzhallen und Unterkünfte

Our translation

construction site facilities including storage halls, protective halls and accommodation

Act
Bayerische Bauordnung (BayBO) in der Fassung der Bekanntmachung vom 14. August 2007 (GVBl. S. 588), BayRS 2132-1-B
Provision
Art. 57 Abs. 1 Nr. 13 Buchst. a
Version of the act
In force from
Text retrieved
Open the official source

Who do you contact?

Untere Bauaufsichtsbehoerde. The building authority of the district or of a town with its own jurisdiction. The governing statute is the Bayerische Bauordnung, not a federal act.

What documents will you need?

  • For a verfahrensfrei project nothing is filed with the building authority. Responsibility for complying with the substantive rules stays with the developer.
  • Evidence of conformity with the local development plan (Bebauungsplan) where one exists for the plot.
  • A gross-volume calculation demonstrating the 75 m3 or 20 m3 line.
  • A site plan with the Art. 6 setback areas where the works sit near a boundary.

How do the neighbouring jurisdictions compare?

How do the neighbouring jurisdictions compare?
JurisdictionBuilt-up areaGross volumeHeightBoundary setbackDo you need a permit or is a notification enough?
Germany, BavariaThe statute states no fixed figure75 m3 · 20 m3The statute states no fixed figure3 mNo filing
Slovakia50 m2The statute states no fixed figure5 m2 mNotification
Czechia40 m2The statute states no fixed figure5 m2 mFull permit
PolandThe statute states no fixed figureThe statute states no fixed figureThe statute states no fixed figureNot yet verifiedNotification

All jurisdictions

What to watch out for

  • The 75 m3 line is a VOLUME, not an area. Most secondary sources restate it as an area threshold, which changes which containers it covers. A 40 ft container is 77.02 m3 and crosses the line by about 2 m3; a 20 ft container is 38.27 m3 and sits safely under it. The arithmetic uses the external dimensions from ISO 668:2020 Table 2.
  • A container on a construction site is judged under a different provision. Art. 57(1) no. 13(a) makes site facilities including storage halls, protective halls and accommodation verfahrensfrei with no volume limit at all, because they are temporarily erected installations rather than buildings. Reading only the 75 m3 limb sends a site cabin into a permit procedure it never needed.
  • Art. 57(1) no. 1(a) states no height limit for buildings. That is why the table shows no height for Bavaria: it is not a gap in our research, it is the fact that this provision does not regulate height. For the same reason no fixed temporary-use period is shown, because the statute sets none for site facilities.

Please note

This is guidance, not legal advice. The thresholds are quoted verbatim from the statute in force on the date shown, but an individual plot can be subject to a zoning plan, a protection zone or heritage rules that are not reflected here. Confirm your case with the named authority before you order.