RESOURCE

Container lead times, from quote to delivery

Catalog stock in weeks, catalog new build in two to three months, custom build in three to four months. What sets the clock, what slows it, and what a buyer can do to keep it short.

RESOURCE · hall view
RESOURCE · weld + paint
RESOURCE · finished unit

Specifications

Welding
ISO 3834-2
Steel
EN 1090 EXC2
Quality
AQAP 2110
Origin
Banovce, SK

Why lead times vary

Steel containers look interchangeable. A quoted delivery date is not. The same hall in Bánovce nad Bebravou can ship a finished 20 ft cube in fourteen days or in fourteen weeks, and the difference has almost nothing to do with the steel itself. It has to do with what happens before the steel is cut.

Three forces set the clock.

First, the configuration. A catalog 20 ft dry cube with single end doors, RAL 7016 paint, and a CSC plate is a known build. Drawings exist, weld procedure is qualified, blast and paint cycle is timed. Capacity is the only variable. A custom build with a side hatch, REI 30 firewall, three compartments, and a non-standard HVAC route is something else. Engineering has to draw it, welders briefed, QA gate longer.

Second, the certifications and documentation chain. CSC plate and ISO 6346 BIC code are standard on our ISO line. AQAP 2110 traceability for a NATO order requires welder qualification records, material certs, and an inspection plan signed at the start. EN 1090 EXC2 is built into the line, but a customer audit pack takes time to assemble.

Third, the queue. A custom build slots into the next open window in engineering, then cutting, welding, paint. Signed drawings on a Monday do not become a steel cut on Tuesday. They become the next available steel cut date.

The numbers we publish are honest. Catalog stock runs 1 to 3 weeks ex works. Catalog new build runs 6 to 10 weeks. Custom build runs 10 to 16 weeks. Framework call-off runs to the framework schedule, which for ARMADA is locked through 2028. What follows is what each window actually contains.

Catalog stock (1 to 3 weeks ex works)

The fastest path. Stock means a finished, certified, CSC-plated container is on the yard at Partizánska 73 in Bánovce nad Bebravou, ready to load. The 1 to 3 week window covers paperwork, transport coordination, and any last-mile livery work.

What sits in stock varies by month. The most-requested configurations are kept available: 20 ft and 40 ft dry cubes in RAL 7016 anthracite, with single end doors, CSC plate, and standard plywood floor. Office and sanitary catalog units in the most common spec also rotate through when the framework line has surplus capacity.

The split, roughly: day 0 to 2 covers the fixed quote, BIC code allocation, and CMR preparation. Day 3 to 7 covers livery or label changes. Day 8 to 14 covers freight booking, EXW handover at Bánovce, and DAP transit inside the EU. DDP runs longer because customs clearance is sequenced after pickup.

If a buyer needs a container in seven calendar days, catalog stock is the only realistic route and the spec has to match what is on the yard. We will say so on the call.

Catalog new build (6 to 10 weeks)

This window applies when the buyer wants a known configuration but stock does not match. The 20 ft cube, 40 ft cube, standard office module, and standard sanitary unit all live in our drawing system. The weld procedure is qualified. The BOM is in our ERP. We do not need engineering time to draw it. We need production time to build it.

Six weeks is the floor. That assumes the buyer signs the quotation in a few working days, the steel for the body and frame is on the rack, the corner castings are in inventory, and the paint booth has a window in the next two weeks. Ten weeks is the realistic ceiling, especially for a long colour cure or a batch consolidating several units onto one production pass.

Within the 6 to 10 weeks, 1 to 2 weeks is queue and order entry, 1 week is cut and bend on the TruLaser 3040 and DURMA press brake, 2 to 3 weeks is welding under EN ISO 3834-2 (robotic on the Daihen FD-V8L lines, manual MIG for fit-out joints), 1 week is blast to Sa 2.5 and two-coat paint in the Polin AC booth, and 1 to 2 weeks is fit-out, FARO QA, BIC code, CSC plate, dispatch.

The window assumes no design changes after the quotation. A door change requested in week three resets the slot in welding and adds two to four weeks. We mention this on the kick-off call.

Custom build (10 to 16 weeks)

A custom build means engineering has to draw it. That is the meaningful difference from catalog new build, and it is where most of the additional time comes from.

Weeks 1 to 3: specification and quotation. We hold the brief in writing, run engineering review, return a fixed price and a target steel cut date. For a configuration close to a family we have built before, the quote turns in 3 to 5 working days. For a true new design, especially with fire rating, hazardous goods, or armoured panels, the quote runs 7 to 10 working days because engineers have to draw enough of the unit to commit to a price.

Weeks 3 to 6: engineering. Shop drawings, BOM, weld procedures (WPS and PQR), QA inspection plan, and a customer sign-off gate before steel is cut. This is the gate where a buyer can change anything cheaply. Once steel is cut, changes cost time and money.

Weeks 6 to 10: production. Same cut, weld, blast, paint, fit-out sequence as catalog new build, with two differences. Welders work to a per-build WPS rather than the catalog standard procedure, which adds setup. The QA gate is longer because the inspection plan has more line items.

Weeks 10 to 16: completion. Documentation pack assembly (CMR, CSC plate where applicable, multilingual manual, material certs, paint cure log, FARO measurement report), final QA, EXW handover or DAP transit. For exports outside the EU, customs and DDP paperwork lengthens the tail.

A 10-week custom build is a single unit, modestly customised, with a buyer who signs the engineering pack on revision one. A 16-week build is typically five or more units with fire rating, electrical and HVAC fit-out, and several engineering revisions before sign-off.

Framework call-off (locked to schedule)

A framework is a multi-year agreement with a published delivery schedule and a locked price book. The buyer issues call-offs against it, each carries an agreed quantity and delivery window, and the production line holds capacity for those windows.

This is how the ARMADA 16.2M framework with the Slovak Ministry of Defence runs through 2028. It is also how the HaZZ Fire and Rescue programme runs for repeat sanitary, laundry, and material transport units. Two follow-on ARMADA orders for 2026 are already signed.

Inside a framework, the lead time for an individual call-off is whatever the framework specifies. Some windows are six weeks, some are twelve, some are tied to a milestone such as a fiscal year end or site readiness date. Pricing is locked. Capacity is reserved. The buyer is not in the catalog queue, they are in their own queue.

A framework only makes sense above a certain volume. Roughly twenty units per year, or a multi-year programme with a defined endpoint, is the floor where lead time security outweighs setup time. Below that, catalog or custom build is the right model.

The 5-step process explained

Every order, whether catalog stock, catalog new build, custom, or framework call-off, runs through the same five steps. The duration of each step changes. The sequence does not.

Step 1, Specification. Use case, dimensions, finishes, certifications, delivery window. NDA in 24 hours if the buyer needs one. For a known family this is a 30-minute call and a written follow-up. For a B2G or defence brief this is a structured document exchange with revision control.

Step 2, Quotation. Engineering review, fixed price, fixed lead time. Typical turn is 3 to 5 working days for standard families, up to 10 for novel designs. The quote is binding once the buyer signs, subject to the spec being held.

Step 3, Engineering. Shop drawings, BOM, weld procedures (WPS and PQR), inspection plan. Customer sign-off gate before steel is cut. This is the only gate where the buyer can change scope cheaply. After this gate, changes cost time. We are direct about this in the kick-off.

Step 4, Production. Cut on the TruLaser 3040, bend on the DURMA AD-S 60400, weld on the Daihen lines or manual MIG to ISO 3834-2, blast to Sa 2.5, two-coat paint to EN ISO 12944 C3, fit-out, FARO 3D measurement at QA. The longest single step on most builds. Also the most predictable, because we run the line in our own hall and do not subcontract welding or paint.

Step 5, Delivery. EXW Bánovce as default. DAP and DDP on request. CMR, CSC plate, multilingual manuals on handover. For exports outside the EU, customs clearance is sequenced after pickup, which adds 1 to 2 weeks on top of transit.

What buyers can do to compress lead time

The single biggest lever a buyer holds is the speed and quality of the specification. The brief that arrives complete in week one is the brief that gets a steel cut date in week three.

Send dimensions, door configuration, livery code, certifications, and delivery destination in the first email. Every missing data point is a round trip, and round trips compound. A complete brief turns a quote in 3 days. An incomplete brief turns a quote in 3 weeks.

Sign the engineering pack on revision one wherever the design is acceptable. The engineering gate exists because changes after steel cut are expensive. The faster the gate closes, the faster the production line opens.

Choose a colour we already hold in the paint booth. RAL 7016 anthracite, RAL 5010 gentian blue, RAL 3000 red, and RAL 9006 are on the standing rotation. Any other RAL is fine, but requires a paint order and a setup change in the booth.

Accept EXW Bánovce nad Bebravou where the buyer has their own freight contract. DAP and DDP add freight scheduling and customs handling that the buyer cannot directly control, and can add 1 to 2 weeks to the headline lead time.

Bundle units into a single batch where possible. Five units of the same configuration in one batch run almost as fast as one unit, because the setup time is shared. Five units of five different configurations is five separate engineering and setup cycles.

Where genuine speed matters more than configuration, buy from stock. The 1 to 3 week ex works window is unbeatable on any new build path, including ours.

What slips lead time

Honesty is more useful than reassurance. The following is what actually slips lead times on our line, in rough order of frequency.

Specification churn after the engineering gate. The most common cause. A door change, new vent spec, or added internal partition after steel is cut typically adds 2 to 4 weeks because the affected sub-assembly has to be re-cut, re-welded, and re-painted.

Delayed customer sign-off on the engineering pack. Drawings sit on a desk for two weeks waiting for a signature. The slot in welding moves. The slot in paint moves. Headline lead time slips by the same number of weeks the signature took.

Material lead time on specialty components. Standard steel sections, weathering plate, marine plywood, and corner castings are in stock or on short reorder. Specialty PIR panels at non-standard thickness, certified fire-rated doors, or specific HVAC units can add 2 to 6 weeks. We flag this in the quotation when it applies.

Paint and cure on non-standard colours. RAL 9005 black and any colour outside the standing rotation needs a paint order and a cure window in the booth. Typically adds 3 to 5 working days.

Customer site readiness on DDP. If the destination site is not ready on the agreed day, the unit waits on our yard at a daily cost or in transit at a higher one. Not a production slip, but it lengthens the gap between quote and operational handover.

Customs paperwork outside the EU. Export documentation is sequenced after pickup. Usually adds 1 to 2 weeks. Destinations with import restrictions on steel structures can run longer.

Holiday windows. Two predictable closures: second half of December plus first week of January, and the last two weeks of August in Slovakia. Builds scheduled across either inherit the closure. We tell the buyer at quotation and adjust accordingly.

We do not pretend any of these are rare. They are the normal texture of running an EN 1090 line at production-level qualification. We publish them so a buyer can plan.

FAQ

How fast can you deliver a 20 ft container? From stock, 1 to 3 weeks ex works Bánovce nad Bebravou, depending on what is on the yard. If your spec matches stock, this is the only single-digit week path we offer.

Why is a catalog new build 6 to 10 weeks if you already have the drawings? The drawings exist. The queue does not skip. A new build slots into the next open window in cutting, welding, blast, paint, and QA. The 6 to 10 weeks is the time the unit physically takes to move through those stations behind the orders already in the queue.

Can you compress a custom build below 10 weeks? Rarely. The engineering pack alone takes 2 to 3 weeks for a true custom design, and production runs at the same physical pace as a catalog new build. Where a buyer needs faster, we look at whether a catalog new build with bolt-on modifications can replace the custom build.

What is the realistic lead time for a B2G framework call-off? Whatever the framework specifies. ARMADA call-offs typically run 8 to 12 weeks. HaZZ call-offs run 6 to 10 weeks for repeat configurations and 12 to 16 for new ones. The point of a framework is that the buyer knows the answer before placing the call-off.

What is the slowest part of a custom build? Engineering sign-off, in our experience. Production time is predictable. The variability sits in how quickly the buyer reviews and signs the shop drawings. We have shipped a 16-week brief in 11 when the customer signed each revision the same week, and a 10-week brief in 14 when sign-off took a month.

Can you give a binding lead time at quotation? For catalog and catalog new build, yes, subject to the spec being held. For custom, we quote a band (for example 12 to 14 weeks) and confirm the steel cut date at the engineering sign-off gate. Framework lead times are written into the framework.

What happens if you miss a lead time? We tell the buyer as soon as the slip is visible, not at the original delivery date. Most contracts include a contractual remedy. The production team plans recovery on the next slot, not the next available month. We have not historically slipped ARMADA or HaZZ call-offs, and we publish these numbers because we hold them.